NOTICE OF ACCEPTANCE
AND FINAL SETTLEMENT
BVJPB 0.5 MG WATER TANK SITE Civil
BRIDGER VALLEY JOINT POWERS BOARD
NOTICE IS HEREBY PUBLISHED that the Bridger Valley Joint Power Board has accepted as completed all work on the BVJPB 0.5 MG Water Tank Site Civil Project according to the plans, specifications and rules set forth between the Bridger Valley Joint Powers Board Stacey Maxfield Construction, the Contractor is entitled to settlement thereof.
Final payment will be made after the completion of publication of this Notice. The date of first publication is September 24, 2026 and the date of final settlement will be after November 4, 2026 and when all punch list items are complete.
Any claim or claims for work or labor due, or for materials or supplies furnished, must be accordingly filed with the Bridger Valley Joint Powers Board prior to the above published date of final settlement.
Bridger Valley Joint Powers Board
P.O. Box 615
Mountain View, WY 82939
PUBLISHED: September 24, October 8, 29, 2026 26162